Cole Avenue House
Project type: New Home
Construction start date: May 2019
Construction completion date: October 2021
Status: Completed/Occupied
The first of two new homes constructed on a lot at the corner of Cole Avenue and Maple Street in Williamstown. This home has three bedrooms and 1200 square feet of living area. Once completed, we built a second home on the adjoining lot.
February 14, 2023
This project was very delayed by COVID-19, but we completed and sold in November 2021 to our selected homeowner, a single mother with an 11-year-old daughter and 8-year-old son.
January 13, 2021
We had hoped to complete this house in Fall 2020, but the COVID pandemic has slowed down our building schedule, first with a three month shutdown last spring, and then with a reduction in the number of volunteers on site to accommodate COVID restrictions.
The exterior insulation and vinyl siding has been completed and the volunteer crew is progressing on interior work. We now hope to have the house completed in late spring or early summer 2021.
November 27, 2019
The trusses are up and braced. The boom truck arrived at 9 AM and by 10 AM the trusses were sitting on the top plates ready to roll up. It was a lot of work, but thanks to Herm we erected the individual trusses by 1 PM. All the trusses have been secured and will weather the wind on Thursday. We drove away just before the rain started.
Thank you to all the volunteers that participated in this critical task.
– Paul Austin, Project Manager
November 23, 2019
The windows are being covered with plastic sheets to protect the interior and to keep the home warm enough to continue working through the cold months ahead.
July 14, 2019
The ground-breaking ceremony for the home now under construction took place on July 14, 2019. The first two pictures show the soon-to-be homeowners, Neil and Megan.